More

    The Borinquen I Geothermal Project Exceeds 40% Construction Progress

    It will provide 55 megawatts of renewable energy to the country

    Must Read

    TCRN STAFFhttp://www.TheCostaRicaNews.com
    Like you, we are tired of corporate media that is politically driven and one sided. So we decided to focus on news that’s important to people. We’re Creating a Conscious alternative news network that we feel the world needs and we need your help! We can’t do this without you! Support news and media that matters and that can help change our world!

     The Borinquen I Geothermal Project continues with the execution of works that will provide 55 megawatts of renewable energy to meet the national electricity demand. Currently, Borinquen I has 40.8% construction progress.  The plant will take advantage of the resource of a deposit located on the slopes of the Rincón de la Vieja Volcano.

     Among the completed works are the access roads, the production and reinjection platforms, the working water storage lagoon and the drilling of seven production wells and five reinjection wells.

     Leonardo Solís, director of the Project, explained that “we have made progress in drilling wells, internal roads, construction of reinjection lagoons, excavation for the Powerhouse and the waste dumps.  Production tests are also continuing, as part of the field evaluation work.”

     In addition, the works to bring energy to the Borinquen I sector will benefit 300 families from CañasDulces and Buenavista, in Liberia, through the construction of a 27-kilometer, 20-megawatt distribution line.

    Eighth ICE plant that uses volcanic steam

    Borinquen I will be the eighth ICE plant that uses volcanic steam.  Costa Rica is the third country on the continent in geothermal capacity to generate electricity, only surpassed by the United States and Mexico, nations with extensive experience in oil drilling.

    Facts in brief:

    • Borinquen I Geothermal Project
    • Location:Cañas Dulces, Liberia, Guanacaste.
    • Installed capacity: 55 megawatts.
    • Effective power delivered: 52 megawatts.
    • Average annual production: 410 gigawatt hours.

         — Entry into operation:2027.

    Relocate to beach work remote
    RESONANCE – Shifting Reality
    For those who have experienced shifts in consciousness and know that more peace, joy, and love awaits in a better living environment. A bold shared vision. A living community and hub for innovation. A sustainable ecosystem for living and working. A model for the new future.
    - Advertisement -
    - Advertisement -

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here

    - Advertisement -

    Subscribe to our newsletter

    Get all the latest news, events, offers and special announcements.

    Latest News

    Costa Rica Improves Its Capabilities to Treat Dangerous Components of Waste Electrical and Electronic Equipment (WEEE)

    The country is preparing for a new WEEE-TON that includes workshops, talks and special awareness campaigns in educational centers...
    - Advertisement -

    More Articles Like This

    - Advertisement -
    Language »